4 W 1 Living room And bedroom 3.35 2.15 3T3S 77.499 Sft
A Aluminium Jindal 28.28 Kg 219 79.92
a bottom track 1.619 20673 3.35 5.42
Side and top track 1.005 20678 7.65 7.69
Handle section 0.642 20707 4.3 2.76
interlock section 0.678 20639 8.6 5.83
shutter top and bottom 0.781 20741 6.7 5.23
Add 5% for wastage 1.35
B Hardware 1 Ls 2083.204 26.88
lock Star 2 nos 62.5 125.00
bearings 6 nos 15 90.00
EPDM ( Make osaka) 19.6 rmt 26.24 514.30
Glass wool 66 rmt 3 198.00
Screws S.S 3''-1'' 49 nos 1.5 73.50
silicon@12/rft /300ml 22 rmt 49.2 1082.40
C powder coating Sft 20 20
D Glass -5mm GT 7.2025 m2 816.27 75.86
Base price as fixed 7.2025 m2 598 4307.095
Add wastage 5% 0.360125 m2 598 215.35475
Add taxes 30% 7.562625 m2 179.4 1356.734925
E Labour for instalation 7.2025 m2 215.28 20.01
Total 222.67
F OH & profits @20% 20% 45
Total 267.67